Oct 14, 2025 POINTS Genaral
  • Visited site for duct installation inspection and hanger spacing verification.
  • Coordinated with civil team on slab openings and supports.
  • Checked pre-commissioning arrangements for chillers and pumps.
  • Recorded non-conformances and rectification actions.
Oct 14, 2025 POINTS Genaral
  • Prepared installation method statements for sprinkler, hydrant, and alarm systems.
  • Defined inspection test plan (ITP) and QA/QC criteria.
  • Scheduled pressure testing and pump commissioning protocols.
  • Coordinated with contractor for first-fix routing works.
Aug 25, 2025 POINTS Genaral
  • Assisted in the processing and certification of the 8th Interim Payment application, verifying claimed works against site progress.