Aug 25, 2025 POINTS FIRE BLOCK 4
  • Monitored the expiry of the Advance Payment Guarantee for Block 4 and assisted in drafting correspondence to the client recommending its encashment due to the contractor's delay.
  • Liaised with the contractor to arrange a three-month extension of the Advance Payment Guarantee with a further reduced value.
  • Assisted in evaluating a new EoT request from the contractor. Analyzed revised reasons for delay, primarily dependency on other contractors for LAN, IBMS, and Smoke Extraction system interfaces.
  • Supported the recommendation to grant a final EoT until 28th February 2024.
  • Liaised with the Block 4 contractor to understand their requirements for extending the Advance Payment Guarantee with a reduced value.