Aug 25, 2025 POINTS FIRE BLOCK 4
  • Continued the shop drawing approval process for the Fire Detection System (Ground, 1st, 2nd, and 3rd Floors).
  • Processed the extension of the contractor's Workmen's Compensation Insurance policy and updated project records.
  • Initiated a request for the contractor to extend the expiring Advance Payment Guarantee.
Aug 25, 2025 POINTS Genaral
  • Completed final coordination drawings for Block 2 GF and 6F, reviewing fire systems and resolving ECT coordination issues.
  • Prepared final coordination drawings for Block 1 (Ground and 4th Floors), including fire, AC, and electrical modifications.