Monthly Diary

Show All Records
Date Title Category Points Actions
Oct 14, 2025 POINTS Genaral
  • Completed detailed heat-load calculations for LL–Roof levels using carrier/ASHRAE methods.
  • Determined envelope heat gains, lighting and occupancy loads.
  • Divided building into HVAC zones for independent temperature control.
  • Selected suitable comfort parameters (24 °C ± 1 °C, RH 50 %).
  • Drafted cooling-load summary sheet and psychrometric chart plots.
Oct 14, 2025 POINTS Genaral
  • Conducted occupancy hazard classification: car-parks (OH-3), offices (OH-2), electrical rooms (No Sprinkler Zone).
  • Established design densities & area of operation.
  • Calculated preliminary fire-water demand for each system.
  • Reviewed existing municipal water availability & pressure.
  • Initiated fire strategy diagram with evacuation zones and firefighting shafts.
Aug 25, 2025 POINTS FIRE BLOCK 4
  • Reviewed the Block 4 contractor's request to remove excess pipe materials from the Block 4 site, linked to the reassessment of their dollar fluctuation claim for Block 4.
Aug 25, 2025 POINTS Genaral
  • Noted the approval of the first Extension of Time (EoT) for the contractor, moving the completion date to 27th May 2024 due to project-wide delays.