Aug 25, 2025 POINTS Genaral
  • (FP8) Identified and formally requested specific builder's work openings (wall penetrations) from the construction team to allow for the installation of pressure relief dampers for the Inert Gas system.
  • (FP8) Assisted the contractor by forwarding their request to the Ministry of Defence for a letter to support a Telegraphic Transfer (TT) to import essential grooved fittings, which were stuck due to new government import restrictions.
  • (FP8) Processed and issued a new Variation Order (VO-03) for the supply and installation of Dry Riser lines.
Aug 24, 2025 POINTS Genaral
  • Studied that a fire suppression system is specially designed to detect and actively control or extinguish fires.