Oct 14, 2025 POINTS Genaral
  • Initiated the MVAC design phase for the building; reviewed architectural layouts and thermal zoning.
  • Defined system objectives – thermal comfort, indoor air quality, energy efficiency.
  • Identified applicable standards – ASHRAE 55, 90.1, 62.1 and CIDA HVAC Code.
  • Conducted preliminary load analysis to estimate cooling capacity for each zone.
  • Prepared initial design schedule, resource plan, and coordination milestones.
Oct 14, 2025 POINTS Genaral
  • Initiated the Fire Protection System Design Program for a multi-storey building (LL1–LL3, GF, 1–6 Floors + Roof).
  • Defined design objectives: life safety, property protection, business continuity.
  • Identified applicable codes – CIDA Fire Code, BS EN 12845, NFPA 13, BS 5839, BS 9999.
  • Collected building architectural and MEP layouts; determined functional zoning.
  • Outlined scope & methodology, including sprinkler, hydrant, hose-reel, and alarm systems.
Aug 25, 2025 POINTS FIRE BLOCK 4
  • Conducted a detailed analysis of the Block 4 contractor's EOT claim, considering impacts on Block 4's progress like import delays and dependencies on other contractors.
  • Recommended a revised EOT for Block 4 to the client, proposing a new completion date of 16th May 2024.
  • Received and processed the critical Fire Precautions Adequacy Certificate for Block 04 from the Fire Service Department.
Aug 25, 2025 POINTS Genaral
  • Assisted in reviewing the geotechnical report for the bollard installation site. Identified that no borehole test data was available at the exact location.
  • Drafted a request to the client (PMU) to arrange a new borehole test to determine the soil bearing capacity, as per CECB Geotechnical Unit's recommendation.
  • Understood the foundation requirements: 2m x 2m reinforced concrete foundation per bollard, requiring a minimum soil bearing capacity of 80 kN/m².