Aug 25, 2025 POINTS Genaral
  • Processed the approval and issuance of a contractor's claim for exchange rate fluctuations (LKR 5.9M) under contract clause 19.1.
  • Received and circulated client instructions to prioritize works for Blocks 03 & 04.
  • Initiated a follow-up request to the client's PMU for detailed payment settlement records to analyze the contractor's interest claim.
Aug 25, 2025 POINTS Genaral
  • Completed final coordination drawings for Block 2 (4th and 5th Floors) and Block 3 LL3, including new duct lines and ceiling updates.