Date Title Category Points Actions
Aug 25, 2025 POINTS Genaral
  • (FP8) Detailed the specific brickwork required around installed fire boxes and risers for the construction team to complete, ensuring architectural finish and compliance.
  • (FP8) Processed and issued the official Supplementary Agreement to the contractor, formalizing the terms for recommencing the suspended works.
Aug 24, 2025 POINTS Genaral
  • Studied that fire safety measures should match the building’s risk profile, with sprinklers, alarms, and signage for low risk; fire-resistant materials, compartmentation, and drills for medium risk; and suppression systems, secure escape routes, and fire-resistant sleeping areas for high risk.