Aug 25, 2025 POINTS Genaral
  • Drafted a formal reminder to the Block 4 contractor regarding their outstanding handover documents for Block 4, specifically the Testing & Commissioning Reports, As-Built Drawings, and Method Statements.
  • Began preliminary review of the Block 4 contractor's request for a substantial (79-day) Extension of Time for Block 4.
Aug 23, 2025 POINTS Genaral
  • Managed and finalized the payment certificate for the elevator installation contract in Blocks 6/7.
  • Attended a professional training course on Welding Technology.