Oct 14, 2025 POINTS Genaral
  • Completed schematic layout for supply and return loops.
  • Determined pipe sizes and insulation thickness.
  • Designed header, manifold, and valve arrangements in plant room.
  • Incorporated isolation, strainers, and balancing valves for zones.
  • Coordinated pipe routing with electrical trunking and fire lines.
Oct 14, 2025 POINTS Genaral
  • Selected addressable fire alarm system architecture.
  • Zoned detectors for LL1–Roof with loop length balance ≤ 200 devices.
  • Integrated cause-and-effect logic for AHU shutdown, pressurization, lift homing.
  • Prepared fire alarm schematic and device layout plans.
  • Coordinated control room panel location and network redundancy.
Aug 25, 2025 POINTS Genaral
  • Contract Administration: Issued Interim Payment Certificate No. 06 for work completed.
  • Technical Coordination: Issued a comprehensive list of essential considerations for the bollard installation, emphasizing multi-disciplinary coordination, adherence to OEM methods, and civil engineering certification for any design changes.
  • Commercial Follow-up: Followed up with the client for formal approval of the evaluated exchange rate fluctuation claim.
  • Contractual Compliance: Notified the contractor to extend the expiring Performance Guarantee and Advance Payment Bond.
  • Site Coordination: Informed the contractor that site clearance was given for them to begin installation works and to verify all service conduits before asphalt laying.