Monthly Diary

Show All Records
Date Title Category Points Actions
Aug 25, 2025 POINTS FIRE BLOCK 4
  • Prepared and issued the 7th Interim Payment Certificate to the client for approval and payment.
  • Formally notified the contractor of the granted EOT until 31st December 2022.
Aug 25, 2025 POINTS FIRE BLOCK 4
  • Assisted in reviewing the contractor's (M/s. DIMO) formal interest claim for delayed payments as per contract clause 16.1.
  • Observed the process of acknowledging a contractor's Notice of Suspension of Work due to payment delays.
  • Documented the initial analysis and correspondence for senior engineer's recommendations.
Aug 25, 2025 POINTS Genaral
  • Issued updated Revit model and final coordination drawings for Block 2 LL3.