Aug 25, 2025 POINTS Genaral
  • Followed up with the Fire Service Department with a second request for a critical site inspection.
Jul 5, 2025 POINTS MVAC BLOCK 4
  • Substantial Completion: MVAC testing by 15th Dec (delayed to 22nd).
  • TAB reports for AHUs submitted.
  • TAB = Testing, Adjusting, and Balancing
  • FCU front panels delivered.
  • Improved crisis management skills amid payment delays.