Aug 25, 2025 POINTS FIRE BLOCK 4
  • Monitored contract guarantees and issued letters to the contractor requesting extension of Advance Payment and Performance Guarantees.
  • Followed up on overdue submittals from the contractor, including look-ahead programs and progress reports.
  • Requested detailed information from the contractor on material/ manpower requirements to complete the project, as discussed in progress meetings.
Aug 25, 2025 POINTS Genaral
  • Prepared final coordination drawings for Block 1 (5th Floor), Block 3 LL2, and Block 4 LL3, including fire hydrant and cable tray modifications.