Aug 25, 2025 POINTS FIRE BLOCK 4
  • Assisted in reviewing the contractor's revised work program and material procurement schedule submitted for the Block 04 Fire Protection system.
  • Observed the initial assessment for the contractor's request for an Extension of Time (EoT) due to material delivery delays caused by import restrictions and foreign exchange issues.
  • Learned about the process of extending bank guarantees, noting the extension of the Advance Payment Guarantee to July 2023.
Jul 5, 2025 POINTS MVAC BLOCK 4
  • Completed final coordination drawings for Block 3 LL2, Block 3 LL3, and Block 4 LL3, adding fire cable trays and main hydrant pipes.
  • LL1/LL2 priority: Ductwork at 50%; chilled water pipes stalled.
  • Staircase extraction fans (approved)
  • Light well ventilation (costing pending)
  • Cash flow issues halted material orders (e.g., harmonic filters).