Oct 14, 2025 POINTS Genaral
  • Compared central chilled-water vs VRF system alternatives.
  • Finalized water-cooled chiller with air-handling unit (AHU) system.
  • Defined primary/secondary pumping and riser configuration.
  • Planned chilled-water pipe routing for LL3 plantroom to roof condenser area.
  • Issued concept drawings for client review.
Oct 14, 2025 POINTS Genaral
  • Designed fire storage tanks for sprinkler + hydrant combined demand (60-min duration).
  • Allocated separate suction & refill arrangements.
  • Planned pump room at LL3 with bund walls, drainage sump, and ventilation ducts.
  • Calculated pump duty points and selected pump types (diesel, electric, jockey).
  • Prepared pump room GA drawing and single-line diagram.
Aug 25, 2025 POINTS Genaral
  • Reviewed and provided feedback on the contractor's technical submissions:
  • Approved in principle the automatic hydraulic tyre killer system.
  • Requested verification of protective coating thickness on site and submission of a corrosion rectification method statement.
  • Requested the OEM's method statement for bollard installation and samples of hydraulic hoses for approval.