Aug 25, 2025 POINTS FIRE BLOCK 4
  • Supported the senior engineer in drafting the recommendation for an EoT until May 2023, citing reasons under Clause 8.4 of the contract.
  • Assisted in the technical evaluation of a proposed brand change for Schedule 40 & 80 pipes ('BLUEPRINT') to mitigate delivery delays.
  • Participated in the initial process of the contractor's claim for exchange rate variation, learning about the required supporting documents (BoL, bank payments).
  • Noted the extension of the Performance Guarantee to align with the new project timeline.
Aug 25, 2025 POINTS Genaral
  • Prepared final coordination drawings for Block 1 LL2, Block 3 LL3, and Block 4 LL3, including fire hydrant and exhaust duct updates.