Monthly Diary

Show All Records
Date Title Category Points Actions
Aug 25, 2025 POINTS FIRE BLOCK 4
  • Monitored the impending expiry of Performance and Advance Payment Guarantees. Assisted in drafting recommendations for their encashment due to the contractor's failure to extend them.
  • Liaised with the contractor and client regarding the procedure for extending the Advance Payment Guarantee with a reduced value.
  • Supported the team in advising the contractor to extend the Performance Guarantee for a further year.
Jul 5, 2025 POINTS MVAC BLOCK 4
  • BMS wiring: 70% at LL3; AHU balancing at 30% (5F-2F).
  • Payment bottlenecks: LKR 243M exchange rate claims pending.
  • Assisted in chiller pipe flushing method statements.