Aug 25, 2025 POINTS FIRE BLOCK 4
  • Assisted in the preparation of Variation Order VO-FP&FD/B4/02 for temporary dry riser works, as per the Memorandum of Understanding.
  • Learned to compile supporting documents for a VO, including Expenditure Analysis Statements.
  • Calculated the cumulative impact of VOs on the original contract value (noted 4.05% increase).
  • Processed the contractor's request for early release of retention money against a bank guarantee.
Jul 5, 2025 POINTS MVAC BLOCK 4
  • Updated Revit model and finalized coordination drawings for Block 1 LL2.
  • Magnetic Bearing Chiller: Online FAT conducted.
  • Extra Works: Light well ventilation, smoke extraction redesign.
  • Documented payment delays’ impact on duct fabrication.