Aug 25, 2025 POINTS FIRE BLOCK 4
  • Processed and issued Interim Payment Certificate No. 10 for LKR 8,608,498.80 based on the contractor's application.
  • Assisted in the detailed assessment of the contractor's claim for an Extension of Time (EoT). Analyzed causes of delay including COVID-19, economic crisis, import restrictions, and delays from other trades.
  • Drafted correspondence notifying the contractor of the approved EoT until 31st December 2023.
  • Reviewed technical submissions for the Inert-Gas Fire Suppression System and emphasized the requirement for a formal method statement for high-pressure pipe installation and testing.