Aug 25, 2025 POINTS FIRE BLOCK 4
  • Monitored site progress and identified that work was falling behind the approved program.
  • Drafted a formal instruction to the contractor under Clause 8.6 to submit a revised method statement to expedite work.
  • Processed and recorded the client's extension of the Advance Payment Guarantee.
  • Liaised with other services to request clearance for ceiling framework installation, confirming our services above-ceiling were complete.
  • Key Learning: Assisted in the technical assessment of a contractor's claim for an Extension of Time (EOT), evaluating factors like Force Majeure (Covid-19) and delays by other trades. Recommended a first EOT until April 2022.
Jul 5, 2025 POINTS MVAC BLOCK 4
  • Completed final coordination drawings for Block 1 LL1 with updated electrical cable trays.
  • Ductwork completed for 5F-2F; LL1-LL3 delayed due to payment issues.
  • BMS conduit wiring finished for 5F/4F.
  • LC delays for VFDs/harmonic filters
  • (Lead time - is the total time between placing an order and receiving the goods.).