Aug 25, 2025 POINTS FIRE BLOCK 4
  • Formally notified the contractor of the granted Extension of Time until 8th April 2022.
  • Issued a second reminder to the contractor regarding slow progress and requested a resource plan.
  • Continued coordinating with other trades for clearances to work in specific areas (5th Floor Conference Hall).
  • Processed and approved shop drawings for the Internal Fire Hydrant System.
Aug 25, 2025 POINTS Genaral
  • Completed final coordination drawings for Block 4 LL3, coordinating all services.
  • Developed the initial Revit model and final coordination for all services in Block 1 LL2.