Aug 25, 2025 POINTS FIRE BLOCK 4
  • Processed and issued an approved Variation Order (VO – FP&FD/B4/01) for additional sprinkler pipe works at LL1 Floor.
  • Advised the contractor to extend the Advance Payment Guarantee for a further six months.
Aug 25, 2025 POINTS Genaral
  • Completed final coordination drawings for Block 2 LL1 (MVAC piping) and Block 3 6F coordination model.