Aug 25, 2025 POINTS FIRE BLOCK 4
  • Intensively involved in site coordination, issuing clearances for ceiling panel installation on multiple floors (VIP 5F, 3F, LL2, 2F, 4F) after confirming our works were complete.
  • Assisted in addressing a site issue regarding lubricant oil leaks from our equipment damaging finished granite floors, prompting immediate corrective action.
  • Requested technical details from the contractor for flexible connectors at construction joints.
  • Attended a progress review meeting and followed up on the action to re-route fire pipes at LL1 & LL2 lobby areas to avoid clashes with the ceiling grid.