HVAC Psychrometric Chart Practice Questions DHQC Block 03 - Tender Study Dashboard
BID NO. DHQC/FP&FD 03/2020 MINISTRY OF DEFENCE DESIGN & BUILD / LUMP SUM

Fire Detection & Fire Protection Systems - Block 03

Defence Headquarters Complex, Akuregoda. An interactive study page summarising the important bidding, commercial, design, installation, testing and pricing requirements contained in Volumes 1-3.

EmployerThe Secretary, Ministry of Defence
Building10 storeys + 3 semi-basements
Approx. floor area48,000 m²
Tender issueSeptember 2020
Historical tender and date warning

The pre-bid and closing dates are original 2020 dates. The document prints bid-validity and bid-security expiry dates that are earlier than the 12 October 2020 closing date. They are reproduced in the clarification section and should be checked against addenda/corrigenda rather than silently corrected.

At a glance

Numbers to remember

The fastest route to the main scale, security and contract obligations.

Estimated cost
LKR 380M
Excluding VAT
Completion period
300
calendar days
Bid security
LKR 5.7M
unconditional, on-demand
Performance security
10%
of Initial Contract Price
Advance payment
20%
of accepted contract amount
Delay damages
0.1%
per day; maximum 10%
Defects period
365
days from Taking-Over
Retention
10%
per IPC; cap 5% of contract
Minimum IPC
LKR 5M
minimum certificate amount
Liquid assets
LKR 114M
minimum after commitments
Tender source: Volume 1, Invitation for Bids, Bidding Data and Contract Data.
Read before anything else

Ten critical tender risks

These clauses have the greatest potential effect on scope, cost, time and compliance.

High risk

1. Complete design responsibility

The Contractor is responsible for the adequacy, detailed design and installation of the whole works. Employer drawings and BOQ are minimum/indicative information, not a transfer of design liability.

High risk

2. Lump-sum contract with no price adjustment

The contract price covers the complete works. The tender states that price adjustment for fluctuation is not applicable.

High risk

3. Omitted or unpriced work is deemed included

Necessary items may be added to the BOQ, but any required item not separately priced is treated as included in the total price.

Commercial

4. Mandatory site familiarisation

The bidder must inspect access, working space, storage, services and local conditions. Lack of knowledge is not accepted as a basis for extras or extensions.

Programme

5. 300-day completion

Coordination, approvals, design development, procurement, installation, testing, training and handover must all fit within the stated completion period.

Claims

6. 28-day claim notice bar

Failure to give claim notice within 28 days removes entitlement to extension of time and additional payment for that claim.

Authority approval

7. Fire authority compliance

The Contractor must obtain required approvals from the Colombo Municipal Council Fire Services Department before, during and after installation, including acceptance/certification requirements.

Interface

8. Extensive systems integration

The fire alarm must interface with smoke control, pressurisation, CCTV, access control, PA, IBMS, lifts, exits, pumps and inert-gas systems. Interface boundaries must be coordinated.

Quality

9. Listed/certified equipment and approvals

New current-model equipment is required. Control panels and peripherals must have the specified independent certification/listing or approval by the Engineer.

Close-out

10. Testing, training and document burden

Trial operation, authority witnessing, full gas discharge testing, classroom/on-site training, manuals, test sheets, reports and as-built records are mandatory deliverables.

Bidder capability

Eligibility and minimum qualification

Failure to satisfy a mandatory requirement may make the bid non-responsive.

CIDA registration

Grade: EM 1
Speciality: Electrical & Mechanical
Sub-speciality: Fire Detection, Protection and Suppression (FDPS)

Vol. 1 - Bidding Data

Bidding route

National Competitive Bidding. Foreign bidders are not permitted. The successful bidder must not be blacklisted.

Vol. 1 - Invitation/Bidding Data

Average turnover

At least LKR 456 million per year for fire detection, fire protection and fire suppression works in any five years of the last ten years.

Vol. 1 - Qualification Criteria

Similar experience

At least five similar systems in the last ten years, including at least one contract valued at not less than LKR 95 million.

Vol. 1 - Qualification Criteria

Financial capacity

Minimum liquid assets/credit, after current commitments and excluding advance, not less than LKR 114 million. Ten years of audited statements are requested.

X = (A - L) - 0.3W + C

Quality & support

ISO 9001:2015 or equivalent is required. Maintenance support in Sri Lanka by the bidder or an authorised agent is compulsory.

Vol. 1 - Bidding Data

Key proposed staff

  • Project Manager: Chartered Mechanical Engineer; 15 years total experience and 5 years in FD/FP works.
  • Senior Mechanical Engineer: Chartered Mechanical Engineer; 5 years total and 3 years in FD/FP works.
  • Site Engineers - 2: B.Sc. Mechanical with 2 years FD/FP, or NDT/HNDE/equivalent with 5 years FD/FP.
  • Technical Officers - 4: NCT/equivalent with at least 2 years FD/FP experience.
Responsiveness

Other decisive conditions

  • !Only one bid may be submitted by a bidder, whether alone or as a JV partner.
  • !A project-specific revolving line of credit must strictly follow the tender form where used.
  • !Certified legal, registration, financial and JV documents must be attached to the A Schedules.
  • !Tender document fee: LKR 50,000, non-refundable, cash.
Three-envelope system

Bid submission structure

Use the checkboxes as a personal study/submission checklist. Their state is saved in this browser.

1

General Information

Administrative, legal, qualification and security documents.

2

Design / Technical Proposal

Compliance, design development, equipment and execution methodology.

3

Financial Proposal

Lump-sum offer using the prescribed price schedule structure.

Original tender timeline

Pre-bid meeting

At the DHQC site, Akuregoda; site visit stated for the same day.

Bid submission deadline

Chairman, Ministry Procurement Committee, Ministry of Defence, Colombo 03.

Bid validity period

The duration is clear; the printed end date is internally inconsistent and requires verification.

Bid security validity

The duration is clear; the printed end date is internally inconsistent and requires verification.

Security

Bid Security - LKR 5,700,000

Must be issued by a reputed commercial bank operating in Sri Lanka and approved by the Central Bank of Sri Lanka. The prescribed unconditional and on-demand guarantee form is to be used, with the Secretary, Ministry of Defence as beneficiary.

MandatoryOriginal formCorrect beneficiaryValidity checked
Contract and cash flow

Commercial terms

Main pricing, security, payment, retention and claims provisions.

TopicTender requirementStudy implicationRisk
Contract priceFixed lump sum, subject only to adjustments allowed by the contract.Price the complete functional system, not merely listed quantities.High
Price fluctuationNo price adjustment; the fluctuation clause is deleted.Long-lead equipment, exchange exposure and inflation must be considered at tender stage.High
Currency / VATQuote entirely in Sri Lanka Rupees. VAT is excluded from rates and shown separately.All other applicable duties, taxes and levies are included.Medium
Design costDesign, review, modification and calculations are not separately priced.Include design resources in item rates/amounts.High
Performance security10% of Initial Contract Price.Allow bank facility and charges.Medium
Advance20% of accepted contract amount against an unconditional on-demand bank guarantee.First instalment stated within 14 days after required security/advance documents, whichever is later.Cash flow
Interim paymentMinimum IPC is LKR 5 million; certified IPC amount stated payable within 28 days after statement/support.Programme valuations to exceed threshold.Medium
Materials payment80% delivered, 90% incorporated and tested, 100% after successful tests and Taking-Over, subject to contract wording.Maintain delivery, installation and testing records.Track
Retention10% from each interim payment, capped at 5% of Initial Contract Price.Include cash-flow effect.Medium
Professional indemnityInsurance limit not less than 5% of Contract Price.Important because the Contractor bears full design responsibility.High
Delay damages0.1% of Initial Contract Price per day, maximum 10%.Protect critical-path procurement, approvals and commissioning.High
Claims noticeNotice required within 28 days; otherwise no EOT or additional payment.Operate a formal early-warning and claim register.High
Pricing rule

Quantities are approximate

The bidder may adjust quantities and add necessary items, but must follow the price-schedule format.

Deemed included

No zero-scope assumption

Required work not listed or not priced is deemed included in the total. Builder's work, fire stopping, handling, storage and protection also require allowance.

Site facilities

Limited Employer provision

Metered water/electricity is chargeable to the Contractor. Standby power and continuity of site supplies are the Contractor's responsibility.

Scope map

System architecture

The Contractor must deliver coordinated, fully operational systems rather than isolated equipment packages.

Field devicesDetectors, MCPs, modules, sounders, phones, switches
Fire Command Centre - Block 03FACP + Firefighter Smoke Control Panel + Video Display + Two-way Communication + Mimic/Status
Building systemsIBMS, CCTV, access, PA, lifts, smoke control, pressurisation, exits, pumps, inert gas
FD

Addressable fire detection

Category L1 and P1 coverage with alarm notification, graphic display and floor/main mimic indications.

Two-way communication

Independent firefighter telephone network with master handset at the Fire Command Centre.

H

Hydrant and sprinkler

Wet riser, landing valves, hose reels, cabinets, sprinklers, valve sets, monitoring and portable extinguishers.

IG

Inert gas suppression

Two engineered full-flooding systems for critical server/NOC spaces, with double-knock actuation and BAS/fire integration.

Technical package 1

Fire detection and alarm

Addressable, networked and integrated fire alarm system for a complete operating building.

System classification

BS 5839 Category L1Category P1Addressable

Life protection and property protection coverage is specified for the building.

FACP capacity

BOQ calls for a wall-mounted FACP with a minimum of ten SLC loops. The technical requirements indicate at least 200 devices per loop, with no more than 80% of capacity used.

Power autonomy

Battery capacity is to support at least 24 hours standby followed by 30 minutes of alarm operation.

Alarm strategy

Two-stage alert/evacuate logic, configurable delays, manual call-point override and alarm verification are included.

Firefighter control

A Firefighter Smoke Control Panel is integrated with the FACP for smoke extraction, staircase pressurisation and automatic openings.

Graphic and mimic display

Video display terminal/printer, main fire mimic and floor mimic panels support rapid alarm location and status monitoring.

Field devices and peripherals
  • Photoelectric addressable smoke detectors, heat detectors and duct smoke detectors.
  • Addressable manual call points, intelligent monitor modules and control modules.
  • Alarm sounders and sounder-strobes; tender-stated sound level is at least 90 dBA at 3 m.
  • Repeater panels, remote indicators, exit/directional signs, batteries and chargers.
  • Short-circuit isolators between zones/floors to limit fault impact.
Wiring and installation
  • Installation is to follow the IET 18th Edition and the specified fire-resisting cable standards.
  • Minimum tender-stated conductor sizes: 1.5 mm² for initiating/SLC circuits and 2.5 mm² for notification circuits.
  • Fire-resisting screened low-smoke cable, with the specified BS 6387 / BS 7629 performance.
  • Detector locations must be coordinated with ceilings, HVAC, lights and architectural finishes.
Two-way firefighter communication
  • Independent addressable-type firefighter telephone system with master handset at the Fire Command Centre.
  • Telephone jacks/outlets at firefighting lobbies and relevant plant areas.
  • System is to support at least five simultaneous handsets, and a cabinet is scheduled with ten emergency handsets.
Programming and records
  • Cause-and-effect programming must cover all listed interfaces, alarm/fault displays, supervisory states and event logging.
  • Printer/event storage and graphic displays are required for operational use.
  • Final programming, labels, zone descriptions, device addresses and cause-and-effect matrix should be reflected in as-built documents.
Technical package 2

Wet riser, hydrant and sprinkler

Design criteria and core equipment values that should be retained for calculations and reviews.

Wet-riser design flow
1,500
L/min (25 L/s)
Landing-valve pressure
4-5
bar
Hose-reel flow
30
L/min
Hydraulic test
15 bar
or 1.5× working pressure, whichever is higher

Hydrant / hose system

  • Wet-riser system with pipes, fittings, valves, landing valves, hoses, nozzles, hose reels and cabinets.
  • 65 mm pressure-regulating landing valves, PN20, generally installed about 900 mm above finished floor level.
  • Three 15 m × 65 mm fire hoses are specified per relevant cabinet/set.
  • Hose reel: 45 m × 19 mm, with tender-stated minimum nozzle pressure of 1.25 bar.
  • Portable extinguishers include 5 kg CO₂ and 9 L water/CO₂ types.

Sprinkler design basis

  • Hazard: Ordinary Hazard Group III.
  • Density: 5 mm/min.
  • Maximum area per head: 12 m².
  • Maximum area of operation: 216 m².
  • Heads: 15 mm quick-response glass-bulb, nominal 68°C; concealed and upright types.
  • Zone flow switches, monitored valve sets and test/drain arrangements are required.
Pipework

Tender-stated material

ASTM A106 Grade B seamless, galvanised, ANSI Schedule 40. Smaller sizes are screwed; larger sizes are grooved as stated in the specification.

Fire stopping

Penetration protection

Pipe and service penetrations are to be sealed with a fire-stopping system providing at least the stated 60-minute rating.

Commissioning

Pressure and functional tests

Hydrostatic testing, leakage inspection, valve/flow-switch operation and complete system testing against available fire mains or the Contractor's own temporary water source.

Technical package 3

Inert gas fire suppression

Engineered full-flooding protection for the Block 03 critical IT/server spaces.

Approx. protected volume
1,850
Design concentration
37.5%
tolerance stated ±5%
Discharge
40-60 s
95% agent discharge
Cylinder size
140 L
at 200 / 300 bar

System configuration

  • Two independent systems serving NOC/server/UPS areas as described in the tender.
  • Common inert-gas cylinder room, with two separate control panels.
  • Gas-status panel at the Fire Command Centre on Lower Level 3.
  • Standby agent quantity sufficient for the largest single risk, permanently connected.
  • Room overpressure venting is the Contractor's design responsibility.

Detection and release logic

  • Addressable double-knock detection.
  • First knock: bells and flashing warning indications.
  • Second knock: sirens/strobes, shutdown/interlocks, door operation and a stated 60-second release timer.
  • Manual mode provides alarms without automatic discharge; dual-action manual release is required.
  • BAS interface by BACnet/IP or Modbus RTU/RS485 for stated system statuses.
Life safety

Occupancy concentration limits

The tender identifies concentration limits for normally unoccupied, evacuated and potentially non-evacuated conditions. Final design must demonstrate compliance with the stated NOAEL/LOAEL criteria.

Acceptance

Full discharge test

A full discharge test is required for each installation, with oxygen/CO₂ logging and witnessing by the Engineer and CMC Fire Services as specified.

Safety provision

Emergency equipment

Two breathing-apparatus sets are specified at each entrance, each with at least 10 minutes' duration, together with warning signs and operating instructions.

Cause and effect

Major integrations and interlocks

The fire alarm is the coordination hub for multiple building systems.

SystemRequired fire response / informationInterface focus
SHEVS / smoke exhaustControl and status monitoring of fans, dampers and automatic openings.Cause/effect, feedback and firefighter override.
Staircase pressurisationStart/control pressurisation fans and monitor operational status.FFSCP switches and indications.
CCTVFire event information for camera focus/response.Agreed protocol and event mapping.
Access controlRelease/unlock relevant doors on fire condition.Fail-safe logic and status confirmation.
Public addressFire alarm override / emergency announcement interface.Priority and evacuation sequence.
IBMS / BASAlarm, fault, supervisory and gas-system statuses.BACnet/IP; inert gas also permits Modbus RTU/RS485 as stated.
LiftsFire recall/control to the stated safe level.Interface relays and confirmation.
Final exit doorsAutomatic opening/release and monitoring.Door hardware, controls and fire strategy.
Hydrant / sprinklerMonitor flow, pressure, valve and pump/sump status signals.Supervisory/alarm categorisation.
Inert gasFirst/second knock, discharged, low-pressure, fault and panel status.Separate suppression logic plus main fire/BAS reporting.
Coordination hold point

Create a signed interface matrix before installation

For every interface, define the initiating event, output owner, input owner, voltage/contact/protocol, normal/fail state, cable responsibility, test method and witness. This reduces disputes between the fire contractor and other service contractors.

Compliance library

Principal standards and approvals

The latest/applicable editions and local authority requirements should be confirmed during detailed design.

BS EN 54Fire detection and alarm equipmentControl panels, sounders, power supplies, heat/smoke detectors and manual call points.
BS 5839-1System design and installationFire detection and alarm systems for buildings.
NFPA 72Fire alarm codeFire alarm and signalling requirements.
BS 5499-4Escape route signsCode of practice for escape route signing.
BS 7629 / BS 6387Fire-resisting cablesLow-smoke and fire-survival cable performance.
BS EN 12845Automatic sprinkler systemsDesign, installation and maintenance basis.
NFPA 2001Clean agent systemsEngineered inert-gas suppression systems.
EN 15004Gaseous extinguishingDesign and application requirements for gas systems.
BS 7273 / BS 5839Gas actuation / detectionRelease logic and associated fire detection.
CIDA / SCASri Lankan fire / E&M requirementsCIDA fire regulations and relevant specialist contractor standards cited in the tender.
CMC Fire ServicesLocal authorityApproval, inspections, tests and certification.
UL / FM / LPCBProduct certificationSpecified listing/certification route, or other institution approved by the Engineer.
Execution roadmap

Design, approvals, testing and handover

A practical sequence distilled from the Employer's Requirements.

Review, verify and develop the design

Inspect the site, review schematic drawings/BOQ, identify additions and submit the complete technical proposal, calculations, equipment data, programme, training and commissioning approach.

Shop drawings and coordination

Prepare detailed layouts, schematics, calculations, cause-and-effect and interface details. Submit at least the stated number of copies for approval before work.

Engineer, product and fire-authority approval

Submit samples and technical literature. Obtain necessary CMC Fire Services approvals and coordinate with architectural, civil, electrical, HVAC, lift, security, PA and IBMS trades.

Approved new equipment only

Use current, defect-free equipment. Factory inspections and tests may be required, with specified costs borne by the Contractor.

Quality, protection and records

Install to approved drawings and manufacturers' requirements; maintain inspection records, red-line information and progress evidence.

Pre-commissioning and integrated testing

Pressure tests, cable/device tests, cause-and-effect, system interfaces, trial operation and all authority/Engineer witness tests.

Classroom and on-site training

Train Employer personnel before handover in routine testing, operation, maintenance, servicing and minor repairs.

Close-out documentation

Submit O&M manuals, commissioning sheets, test reports, as-built drawings and required soft copies within the stated period after Taking-Over.

Progress control

Monthly progress reports and a next-month look-ahead programme are required. Failure to revise an unacceptable programme/method statement can lead to an additional 5% retention until approval.

Handover quantities

General Employer's Requirements state: 5 O&M manuals, 5 commissioning-sheet sets, 5 test-report sets, 5 hard-copy as-builts and 5 soft-copy sets, within 30 days of Taking-Over.

Maintenance proposal

Terms and charges for a service and maintenance contract are to be submitted with the bid.

Volume 3

Indicative BOQ magnitudes

Key quantities for understanding project scale. These are not a substitute for pricing every BOQ page and design obligation.

Smoke detectors
1,260
photoelectric addressable
Manual call points
118
addressable
Sounders + strobes
191
138 sounders + 53 sounder-strobes
Sprinkler heads
6,639
calculated from floor BOQ quantities

Fire detection - selected quantities

Smoke detectors
1,260
Heat detectors
45
Duct detectors
34
Manual call points
118
Sounders
138
Sounder-strobes
53
Floor mimic panels
40
Phone outlets
40

Fire protection - selected quantities

Concealed sprinklers
4,363
Upright sprinklers
2,276
Landing valves
46
Fire hose sets
46
Hose reels
48
CO₂ extinguishers
110
Water/CO₂ extinguishers
180
Zone valve sets
10

Principal control equipment

1 FACP (minimum 10 loops), 1 Firefighter Smoke Control Panel, 2 repeater panels, 1 video display terminal, 1 main mimic and 40 floor mimic panels.

Preliminaries

The BOQ includes a provisional sum of LKR 3.8 million for insurance, alongside bonds, temporary office, utilities, storage and site security items.

Inert gas pricing

The main inert-gas system is priced as a complete design/supply/installation item, plus a testing and commissioning item. Detailed completeness remains the Contractor's responsibility.

Do not overlook

Document inconsistencies / clarification points

These are source-document issues identified during study. They should be resolved by formal clarification/addendum, not assumption.

1

Bid-validity calendar date

The document states a 119-day validity from 12.10.2020 but prints an end date of 07.02.2020, which is before the closing date. The duration and printed date conflict.

2

Bid-security calendar date

The document states 147 days from 12.10.2020 but prints an end date of 07.03.2020, also before the closing date. Confirm the intended year/date.

3

As-built soft-copy quantity

Volume 2 general handover requirements state 5 soft-copy sets, while a Volume 3 BOQ item is stated as 3 soft-copy CDs. Confirm the controlling quantity or adopt the more stringent requirement pending clarification.

4

Inert-gas zone wording

The specification wording associates the UPS room with both System 1 and System 2. Confirm the actual room zoning and whether there are separate UPS rooms/volumes.

5

Drawings and interface boundaries

Drawings are bound separately and other services are under separate contracts. Confirm all control-panel locations, interface points, cable routes, builders' work and scope boundaries against the issued drawings.

6

Standards editions / authority interpretation

The tender cites specific and “latest” standards in different places. Confirm the applicable edition hierarchy and any current CMC Fire Services requirements before detailed design.

Active recall

Flashcards and quick test

Click a flashcard to reveal its answer, then complete the ten-question test.

What is the Time for Completion?
300 days
What is the bid security?
LKR 5.7 million, unconditional and on-demand.
Who carries complete design responsibility?
The Contractor. Employer drawings/BOQ indicate minimum requirements.
Sprinkler hazard classification?
Ordinary Hazard Group III, 5 mm/min and 216 m² maximum area of operation.
Fire alarm standby duration?
24 hours standby + 30 minutes alarm.
Inert-gas design concentration?
37.5% with tender-stated ±5% tolerance.

1. The estimated tender cost excluding VAT is:

2. The minimum CIDA grade is:

3. The contract price is best described as:

4. Maximum delay damages are:

5. The claim notice period is:

6. The sprinkler hazard group is:

7. The wet-riser design flow is:

8. The fire alarm standby requirement is:

9. The inert-gas actuation philosophy is:

10. Unpriced but necessary work is:

Source map

Where to return for full detail

Use this dashboard for navigation and revision; consult the original clauses, schedules and drawings for decisions.

VOLUME 1

Administrative & contract

  • Instructions to Bidders
  • Conditions of Contract and standard forms
  • Invitation, Bidding Data and Contract Data
  • Form of Bid and A Schedules
  • Qualification, security, submission and commercial terms
VOLUME 2

Employer's Requirements

  • General design and execution requirements
  • Fire detection and two-way communication
  • Hydrant, sprinkler and extinguisher systems
  • Inert-gas suppression
  • Technical proposal and B Schedules
VOLUME 3

Price proposal & BOQ

  • Form of Price Proposal
  • Pricing preambles
  • Preliminaries
  • Fire detection BOQ
  • Fire protection and inert-gas BOQ
  • C Schedules and bidder checklists
No matching topic found.
Try a shorter term such as “sprinkler”, “payment”, “security” or “testing”.