Fire Protection Plumbing Quick Reference Guide Technical Proposal: Make-Up Water System for Condenser Water Cooling Towers

Technical Proposal: Make-Up Water System for Condenser Water Cooling Towers

1. Executive Summary

This proposal outlines the design and implementation of a make-up water system for condenser water cooling towers serving a 2555 TR chiller plant. The system is designed to maintain optimal water quality and quantity for the condenser water loop operating with a 5°C ΔT (37°C-32°C) temperature difference.

2. System Requirements

Key Design Parameters:

3. Water Loss Calculations

3.1 Evaporation Loss (E)

E = 0.00153 × R × ΔT × C (for °C)

Where:
R = Recirculation rate = 1066.5 m³/hr
ΔT = Temperature difference = 5°C
C = Cooling tower capacity factor = 1 (for design conditions)

Calculated Evaporation Loss: 0.00153 × 1066.5 × 5 × 1 = 8.16 m³/hr or 195.8 m³/day

3.2 Drift Loss (D)

Assuming high-efficiency drift eliminators (0.001% of recirculation rate):

D = 0.00001 × 1066.5 = 0.0107 m³/hr or 0.26 m³/day

3.3 Blowdown (B)

B = E/(C-1), where C = cycles of concentration (assume 5)

B = 8.16/(5-1) = 2.04 m³/hr or 49.0 m³/day

3.4 Total Make-up Water Requirement

M = E + B + D

M = 8.16 + 2.04 + 0.0107 = 10.21 m³/hr or 245.0 m³/day

Design Basis: System sized for 250 m³/day capacity with 20% safety margin

4. System Design Specifications

4.1 Treatment System Capacity

Component Design Parameter Value
Make-up Water Pumps Capacity (2 duty + 1 standby) 12 m³/hr each
Storage Tank Minimum capacity 50 m³ (20% of daily requirement)
Filtration System Multi-media filters 15 m³/hr capacity
Softening System Ion exchange 12 m³/hr capacity

4.2 Water Quality Targets

Parameter Target Value Maximum Allowable
Total Hardness (as CaCO3) < 50 ppm 100 ppm
Total Dissolved Solids < 500 ppm 1000 ppm
Chlorides < 100 ppm 250 ppm
pH 7.5-8.5 6.5-9.0

5. Piping and Instrumentation

6. System Hydraulics

Parameter Value
Total Dynamic Head 3.5 bar
Pump Power Requirement 3 kW per pump
Velocity in Main Headers 1.8 m/s (design max 2.4 m/s)

7. Implementation Schedule

  1. Detailed Engineering: 3 weeks (including hydraulic calculations)
  2. Equipment Procurement: 6 weeks (long lead items identified)
  3. Installation: 4 weeks (parallel with chiller plant operations)
  4. Commissioning: 2 weeks (including water quality testing)

8. Appendices